According to the latest schedule, T-50-5R should make the first flight of 22.08., Transfer OKB 06.09. OChK (wing parts) for T-50-7 should be transferred to Zhukovsky by 30.09. Meanwhile, during static testing of T-50-7 fuselage identified the need to strengthen the frame №23. Thus the timing of construction of T-50-6-2 significantly shifted. Now, the first flight will take place on October 5 and the transfer to OKB - 28 December. Such a large gap between these dates is due to the fact that the first plane that will have a fully applied RAM . T-50-8, respectively, shifts to 2016.